The National Times - North Chennai Power Project Cost Surges Nearly 80% to Rs 11,290 Crore

North Chennai Power Project Cost Surges Nearly 80% to Rs 11,290 Crore


North Chennai Power Project Cost Surges Nearly 80% to Rs 11,290 Crore
North Chennai Power Project Cost Surges Nearly 80% to Rs 11,290 Crore

Tamil Nadu’s power generation and distribution corporations have petitioned the state regulator for approval of a revised capital investment plan for the North Chennai Thermal Power Station (NCTPS) Stage III project. The total cost has escalated by nearly 80 percent from its original estimate, reaching Rs 11,286.40 crore due to significant execution delays and rising interest costs.

Change text size:

Tamil Nadu’s power utilities have submitted a petition to the Tamil Nadu Electricity Regulatory Commission (TNERC) seeking approval for a revised capital investment plan for the North Chennai Thermal Power Station (NCTPS) Stage III project. The proposed outlay of Rs 11,286.40 crore represents an escalation of nearly 80 percent from the initial estimate of Rs 6,357 crore.

The petition, filed by Tamil Nadu Power Generation Corporation Ltd (TNPGCL) and Tamil Nadu Power Distribution Corporation Ltd (TNPDCL), requests regulatory clearance for the revised financial plan covering the 2026-27 financial year. The 800 MW unit was inaugurated by the then chief minister on March 7, 2024, and commenced commercial operation on January 24 of this year.

The cost trajectory of the project has shown a steady upward trend over the past decade. Initially estimated at Rs 6,357 crore in 2012, the projected cost was revised to Rs 7,129.56 crore in 2019. It was further raised to Rs 8,722.86 crore in 2022 and reassessed at Rs 10,158 crore in February 2024. The latest proposal adds an additional Rs 1,128.40 crore for completing balance works, bringing the total to Rs 11,286.40 crore.

Utilities attributed the substantial cost escalation primarily to delays in project execution, increased interest during construction (IDC), higher fuel prices, additional scope of work, and technical problems encountered during the construction phase.

A significant setback contributing to these delays was the withdrawal of the original Balance of Plant (BOP) contractor, BGR Energy Systems Ltd. According to the petition, the company, which had been awarded a Rs 2,600.02 crore contract in October 2016, stopped work on February 2, 2024, and left the project site without prior intimation. The contract was subsequently terminated on July 18, 2025.

Remaining works were awarded to CREW Pvt Ltd on July 21, 2025, for Rs 1,128.40 crore, including taxes, with a completion period of 24 months. The corporations noted that the project was originally scheduled to be commissioned within 42 months, with October 2019 set as the target date. However, slow progress by both the Boiler-Turbine-Generator (BTG) and BOP contractors, inadequate deployment of manpower and machinery, and delays in critical activities pushed the schedule back.

The construction timeline was further disrupted by the Covid-19 pandemic in 2020 and 2021. Lockdowns, restrictions on material movement, labor shortages, and delays in mandatory inspections hampered progress. Additionally, technical problems, including damage to erected cooling-water pipelines and malfunctioning cooling-water pumps, necessitated time-consuming rectification work that affected other key project activities.

The most significant component of the cost increase is interest during construction, which rose from the previously approved Rs 1,335.88 crore to Rs 2,355 crore. This represents an increase of more than Rs 1,019 crore, or over 76 percent. Fuel expenditure also saw a substantial rise, increasing from the approved Rs 252.20 crore to Rs 549.29 crore. The utilities cited rising prices of high-speed diesel, heavy fuel oil, and imported coal as the primary drivers for this increase.

The revised estimate also includes Rs 151.89 crore towards additional works, which encompass an additional coal-handling system, dust screens, additional silos, and security arrangements.

Amid these developments, Tamil Nadu is also planning to procure 3,000 MW of power over five years due to concerns regarding the El Nino weather phenomenon. Separately, the cost of the Udangudi power project has also risen by Rs 1,495 crore, reflecting broader trends in infrastructure project financing within the state.

R.Evans--TNT